Northern Ireland

Brockaghboy wind farm

Location: Nr Gavagh, County Londonderry
Project Capacity: 47.5MW
Turbines: 19 x Nordex N90 2.5MW wind turbines
Dimensions: Overall height to blade tip = 125m
Status: Operational since 2018
Owner: Greencoat UK Wind

Crockbaravally wind farm

Location: Nr Sixmilecross, County Tyrone
Project Capacity: 7.5MW
Turbines: 3 x Nordex N100 2.5MW wind turbines
Dimensions: Overall height to blade tip = 125m
Status: Operational since 2016
Owner: Ingenious Renewable Energy

Dunmore wind farm

Location: Limavady, County Londonderry
Project Capacity: 21MW
Turbines: 7 x Vestas V90 3MW wind turbines
Dimensions: Overall height to blade tip = 125m
Status: Operational since 2014
Owner: Capital Dynamics

Dunmore 2 Wind Farm

Location: Limavady, County Londonderry
Project Capacity: 24MW
Turbines: 8 wind turbines
Dimensions: Overall height to blade tip = 126m
Status: Under development
Owner: TCI Renewables

Ballyutoag wind farm

Location: Belfast
Project Capacity: 11.75MW
Turbines: 5 x wind turbines
Dimensions: Overall height to blade tip = 92.5m
Status: Operation expected 2024
Owner: BSI Wind

Pigeon Top wind farm

Location: Drumquin, County Tyrone
Project Capacity: 38.4MW
Turbines: 9 x wind turbines
Dimensions: Overall height to blade tip = 142.5m
Status: Operation expected 2024
Owner: Energia

Clondermot wind farm

Location: Clondermot, County Londonderry
Project Capacity: 2.3MW
Turbines: 1 x Enercon E70 2.3MW wind turbine
Dimensions: Overall height to blade tip = 110m
Status: Operational since 2015
Owner: Energia

Lisglass wind farm

Location: Ballyclare, County Antrim
Project Capacity: 2.3MW
Turbines: 1 x Enercon E70 2.3MW wind turbine
Dimensions: Overall height to blade tip = 100m
Status: Operational since 2015
Owner: Energia

Antrim Area Hospital

Location: Antrim, County Antrim
Project Capacity: 0.66MW
Turbines: 1 x Vestas V47 660kW wind turbine
Dimensions: Overall height to blade tip = 63.5m
Status: Operational since 2005
Owner: Antrim Area Hospital

Robinson Quarry

Location: Ballymena, County Antrim
Project Capacity: 0.25MW
Turbines: 1 x EWT DW 52 250KW wind turbine
Dimensions: Overall height to blade tip = 76m
Status: Operational since 2012
Owner: Robinson Quarry Masters